IAEA to review controversial Taishan plant safety before launch

The International Atomic Energy Agency will conduct a pre-operational safety review at the controversial Taishan nuclear power plant early next year

國際原子能機構

The International Atomic Energy Agency (IAEA) will conduct a pre-operational safety review at the controversial Taishan nuclear power plant early next year.

The IAEA, an intergovernmental organisation promoting the safe, secure and peaceful use of nuclear technologies, will send an Operational Safety Review Team (OSART) of international specialists with senior-level nuclear operator experience to assess Taishan’s safety performance using the IAEA’s Safety Standards, “proposing recommendations for improvement where appropriate and [producing] a report shared with hosts”, the IAEA told FactWire.

An OSART mission is a three-week on-site review of a plant’s operation and safety performance, during which experts “conduct interviews with plant staff, observe plant workers, and analyse documents related to plant operation”, the organisation’s website explains. “It is not a regulatory inspection, nor is it a design review or a substitute for an exhaustive assessment of the plant’s overall safety status”, a spokesperson said.

The IAEA said the review was requested by Chinese authorities. The IAEA did not say exactly when the request was made. A request must be made at least 18 to 24 months in advance of the mission. The spokesperson said the review report was expected to be delivered to authorities before the plant begins operating, adding that governments usually invite a follow-up mission within two years of the initial mission.

Founded in 1982, IAEA’s OSART programme has reviewed almost every type of nuclear reactor and over 150 nuclear power plants, including China General Nuclear Power Group’s (CGN) plants at Daya Bay, Ling Ao, and Hongyanhe plants. CGN owns and manages the Taishan plant.

Scheduled to launch next year, Taishan uses third-generation European Pressurised Reactor (EPR) technology, the most advanced in the world. According to CGN’s online information, key operators of the Taishan plant, including radioactive fuel operators, are trained by CGN in Shenzhen’s Daya Bay. Official CGN sources claim the Shenzhen training centre is the world’s only centre outside of France that trains, tests and certifies radioactive fuel operators through reality-based simulation. CGN launched the training centre in February 2014, and certified its first group of Taishan operators in December of that year.

MISSING IMAGE
First group of operators of Taishan Nuclear Power Plant received their certifications in December 2014. (Photo: CGN)

FactWire earlier reported that the first two reactors at the Taishan nuclear power plant had been sealed despite safety concerns about reactor components, and were scheduled to launch in the first half of 2017 as planned.

Developed by French company AREVA, the manufacturing process of the reactor pressure vessel has been found to be inherently flawed, causing safety concerns about the reactor pressure vessels used in Taishan.

In addition, the reactor pressure vessel of both reactors were not French-made, as was previously believed, but were instead manufactured by Japan’s Mitsubishi Heavy Industries and China’s Dongfang Electric Corporation.

CGN has not yet responded to FactWire’s requests for comment.

Other stories

LeaveHomeSafe app has built-in facial detection module, government admits

李家超李文龍合照 Photo of John Lee and Gilbert Lee together

Business connections of John Lee’s sons with CE electors revealed

李家超 John Lee

John Lee’s first two properties incurred over $8m profit in the 90s

First instance of Wuhan Huoshenshan blueprint with restricted exterior access being built in Hong Kong’s Lok Ma Chau Loop

omicron-vaccine

CoronaVac limits Hong Kong’s protection against Omicron, even if entire population were to be vaccinated

omicron-vaccine-3rd-dose

Government puts little emphasis on local experts’ advice to opt for Comirnaty booster

relaunch hong kong

Surveyed Japanese react unfavourably to Hong Kong in $44m rebrand research

relaunch hong kong

Negative views on Hong Kong’s democracy and freedom revealed by 2020 publicity analysis

FW-PIX-2021-LEGCO-ELECTION-PRIVILEGED-1-864x500

41 Privileged voters’ power is 7,200 times a single-vote holder’s under new LegCo electoral system

Government’s broken promise: Original clock not required in the reconstructed old Star Ferry Clock Tower

Records show long hours of unplanned shutdown caused by ‘human factors’ in Taishan Unit 1’s first year of operation

17 High-salt/sugar foods qualify for government’s salt/sugar-reduction label scheme

Lands Department contradicts itself about SOGO’s possible land term violations

CCTV installed in two primary school’s classrooms but parents say they do not know

SOGO CLUB failed to follow its ‘members only’ license requirements for years