West Kowloon authority hid expenses for Palace Museum in other contracts, documents reveal

The West Kowloon Cultural District Authority did not make public details about advance funds for the Palace Museum project

170123-864x500

The West Kowloon Cultural District Authority (WKCDA) did not make public details about advance funds for the Palace Museum project, yet consulted the engineering firm Ove Arup & Partners about “additional ground investigation (GI) works” for the project in September last year, WKCDA internal documents show.

The documents show that the works cover areas including “Project P” and “Public Infrastructure Works (PIW)”, meaning that the WKCDA could have been involved in other contract deals, unknown to the public, to carry out the advance works for the project.

Aside from the $4.5 million commission to architect Rocco Yim Sen-kee to carry out a feasibility study, no other advance funds for the project have been announced by the former chairman of the board of WKCDA, Carrie Lam Cheng Yuet-ngor.

Yim’s architectural firm, Rocco Design Architects, commissioned Arup to be the consultant for construction works prior to the firm’s own commission by the board of WKCDA to be the design consultant for the Palace Museum project, FactWire can confirm.

WKCDA internal documents state that in September last year, the WKCDA asked Arup to provide “additional ground investigation works” for the “Developments at the Exhibition Hub Area (EHDA)”. The document further states that the scope of the GI works consists of “9 no. of ground investigation boreholes at the Project P area” as “supplement to the previous phase of GI works”, as well as adding 17 boreholes within the PIW site area to “produce the GI information of the future road and transfer structure above the Western Harbour Crossing” for that area. The expected cost was $3 million and there were six invited tenderers for the GI works, the document shows.

Details of the documents resemble West Kowloon’s planned infrastructure works in 2013.

Meanwhile, records of West Kowloon’s tender notices provided by Tanya Chan Suk-chong, deputy chairman of the Legislative Council Joint Subcommittee to Monitor the Implementation of the West Kowloon Cultural District Project, to FactWire, show that on January 3 2017, there were only tender records of contracts awarded in August and November last year on West Kowloon’s website. The GI contract awarded to Bachy Soletanche Group Limited on October 28 last year was not listed. On January 20, FactWire reporters found details of the GI contract on the website, which means that the WKCDA updated and added the GI contract details back on its website between January 4 to 20. The information was not made known to public for almost two months.

FactWire acquired a “Proposed West Kowloon Cultural District Project P Ground Investigation Plan” that is addressed to Arup from the WKCDA. Comparing it to the plan for the “Infrastructure works for West Kowloon Cultural District, phase 1- design and site investigation” approved by Legislative Council (LegCo) in 2013, the 17 boreholes within the PIW site area are situated at the proposed at-grade road area. The infrastructure works project was entrusted by the government to the WKCDA for design and GI works.

Sources said that the WKCDA internal documents clearly state that the investigation work is “additional” and a “supplement to” the previous stage of GI works, and that the department responsible for procurement and contracts in the WKCDA was also informed about the arrangements. It raises the possibility that the WKCDA and Arup had already signed a contract and requested additional GI works, without public knowledge.

Construction industry professionals told FactWire that government projects should be transparent.

“If a large scale construction involves smaller projects at different stages, industry professionals will sometimes use funds from one project [for] another project to carry out advance work, to skip administrative procedures and save time. While it is not unusual for private companies, it is still, strictly speaking, not correct practice. It would be a serious problem if government projects operate like this, since it would lead to a mismatch between the budget and the allocation of funds.”

FactWire acquired the report of “Additional Ground Investigation for the EHDA”, which states that the contractor Bachy Soletanche Group was commissioned last year on October 28 and began the GI works in early November. The location of the nine boreholes stated in the report are precisely in the proposed site where the Palace Museum would be built. Arup gave the report to Rocco Design and WKCDA in late December last year. The WKCDA website shows that Bachy Soletanche Group was awarded a $1.74-million contract on the additional ground investigation works for developments at Exhibition Hub Area. It does not mention Arup as the consulting firm, the details of the contract and payment. 

Official documents state that the government financed an upfront endowment of HK$21.6 billion to WKCDA in 2008 for construction and operation of the district, and the government would be responsible for spendings on public infrastructure.

LegCo’s Finance Committee approved the “Infrastructure works for West Kowloon Cultural District, phase 1- design and site investigation”, and a budget of $478 million to support the design and site investigation in 2013. The government later entrusted to the WKCDA the design and ground investigation of part of the infrastructure works, which cost a total of $260 million, including consultant fees of $184 million and ground investigation works of $39 million.

FactWire also acquired Arup internal documents, which show that Arup may have been working on the Palace Museum project before Yim was appointed. 

Sources from Arup states that Arup was commissioned by Rocco Design to carry out a feasibility study on an arts project in West Kowloon on November 8 last year, 20 days before the board of WKCDA appointed Yim as the design consultant of the Palace Museum project. The commissioned project is also titled as “Project P”. The scope of services include structural, geotechnical and mechanical engineering and last for 2 years.

The project manager, Paul Tsang Sau-chung, is the director of Arup in Hong Kong. Tsang also participated in the construction works for the M+ Building in West Kowloon.

FactWire contacted Tsang last Wednesday (January 18). He said  it was “not convenient” and hung up when asked to comment on the West Kowloon projects. FactWire also made inquiries at Arup’s office. After asking reporters to wait for one and a half hour, staff refused to answer questions, stating that the company “never responded to any inquiries on company projects”.

The board of WKCDA gave the codename “Project P” to the Palace Museum project and commissioned Yim to carry out the design and valuation work in June last year. However, it was not until last October that the Hong Kong Jockey Club Charities Trust approved a donation of $3.5 billion for the project.

Lam, then chairman of the HKCDA board, told a press conference on January 10 that the WKCDA had commissioned Yim for a fee of $4.5 million to carry out a feasibility study, valuations and to propose design concepts. No mention was made of any other fees concerning the project. 

Lam resigned as Chief Secretary on January 13 and the present Chief Secretary Matthew Cheung Kin-chung took up the position of the chairman of the WKCDA board.

The government allocated funds of $21.6 billion to the WKCDA in 2008 to build a cultural district. Forecasting an overrun in the actual building costs, the government was aware of the need to establish public-private partnerships and seek donations. WKCDA staff told FactWire that they did not know about the $4.5 million fund for Yim’s commission until the day of the press conference. They believed the commission would affect West Kowloon’s budgets and operations.

“People in the company have been very nervous about the costs, and constantly make requests to tone down the scale of some cultural arts programmes in order to afford West Kowloon’s project expenditure. The $4.5 million that was suddenly gone is equivalent to the budget of 3-4 large-scale projects,” the WKCDA staff members told FactWire.

Construction industry professionals told FactWire that Lam’s explanation was vague and unclear. “It is impossible for solely the architect to carry out the feasibility study and valuation on his own since many other professional services, such as site investigation works, quantity surveying, environmental and pedestrian flow assessments are involved. Did the $4.5 million already include the total cost, or were some services outsourced, and if so, how much are they? Were they paid by public funds?”

According to the WKCDA’s annual reports and tender notices, Arup, along with Swiss architectural firm Herzog & de Meuron and Hong Kong-based TFP Farrells, has been working together since August 2013 on the construction works of the M+ Building. The foundation work began in August 2014, and the main superstructure work of the building began in late 2015 and is scheduled for completion in 2018.

Arup, the government’s consulting firm for the Wang Chau housing development project, was suspended from tendering for three months in November 2016, after violating contract terms by accepting an offer from New World Development to provide them with consulting services for the housing projects in Wang Chau, and using confidential information obtained from the government without official authorization. Although Arup could not participate in the bidding of consultant contracts under the “Engineering and Associated Consultants Selection Board”, contracts under the WKCDA was not under management of the selection board and thus are not affected by the suspension order.

This story is republished or cited by:

South China Morning Post   

Other stories

LeaveHomeSafe app has built-in facial detection module, government admits

李家超李文龍合照 Photo of John Lee and Gilbert Lee together

Business connections of John Lee’s sons with CE electors revealed

李家超 John Lee

John Lee’s first two properties incurred over $8m profit in the 90s

First instance of Wuhan Huoshenshan blueprint with restricted exterior access being built in Hong Kong’s Lok Ma Chau Loop

omicron-vaccine

CoronaVac limits Hong Kong’s protection against Omicron, even if entire population were to be vaccinated

omicron-vaccine-3rd-dose

Government puts little emphasis on local experts’ advice to opt for Comirnaty booster

relaunch hong kong

Surveyed Japanese react unfavourably to Hong Kong in $44m rebrand research

relaunch hong kong

Negative views on Hong Kong’s democracy and freedom revealed by 2020 publicity analysis

FW-PIX-2021-LEGCO-ELECTION-PRIVILEGED-1-864x500

41 Privileged voters’ power is 7,200 times a single-vote holder’s under new LegCo electoral system

Government’s broken promise: Original clock not required in the reconstructed old Star Ferry Clock Tower

Records show long hours of unplanned shutdown caused by ‘human factors’ in Taishan Unit 1’s first year of operation

17 High-salt/sugar foods qualify for government’s salt/sugar-reduction label scheme

Lands Department contradicts itself about SOGO’s possible land term violations

CCTV installed in two primary school’s classrooms but parents say they do not know

SOGO CLUB failed to follow its ‘members only’ license requirements for years